RateProof Capacity Study

Capacity study template, field by field

Every capacity study needs the same fields and the same formulas, whether it lives on paper, in a spreadsheet or in an app. This page lists them, fills them in for a three operation line, and explains why a copied spreadsheet slowly stops computing what it claims to.

Need it working now? The free capacity verification calculator is this template with the formulas running. Enter your operations and it works out net available time, effective cycle time, demonstrated capacity, the requirement at each operation, both utilization measures, the risk band and the constraint.

The fields a study needs

A template has three parts: what the study is about, what you enter for each operation, and what the formulas make of it. When and how to collect the inputs is covered in how to run a capacity verification study.

About the study

Part number and name
The part the study covers. Several part numbers built on the same line add their daily volumes together.
Supplier, site and engineer
Who ran the study, at which plant.
Date of the run
When the cycles were timed and the run was tallied.
Required parts per day
The customer's contracted volume, converted to a daily rate over the working pattern the line runs.
Notes
Anything a reviewer needs to judge the evidence: crew, material, anything unusual about the run.

Entered for each operation

FieldUnitWhat goes in it
OperationnameIn process order, the final operation last.
Shifts per daycountFractions are allowed: two and a half shifts is 2.5.
Hours per shifthoursScheduled hours, before any downtime.
Parallel machinescountMachines running this same operation at the same time.
Parts per cyclecountCavities, nests or basket size.
Breaks and lunchminutesPer machine per day, whenever the machine stops for them.
Changeoverminutes, daysMinutes for one changeover and the days between them. One 45 minute changeover every two days costs 22.5 minutes a day.
Planned maintenanceminutesPer machine per day.
Other planned downtimeminutesStart up, material changes, meetings: any other scheduled stop.
Unplanned allowanceminutesAn honest estimate of unplanned stops. Never zero.
Measured cycle timesecondsThe average of cycles timed at the line, with the timed cycles kept as evidence.
Scrap ratepercentParts this operation makes that cannot ship.

Calculated for each operation

Scrap rates enter these formulas as fractions: 1.5 percent is 0.015.

Scheduled minutes
Shifts per day × hours per shift × 60, for each machine.
Planned downtime
Breaks and lunch + changeover minutes ÷ days between changeovers + planned maintenance + other planned downtime + unplanned allowance, for each machine.
Net available time
(Scheduled minutes minus planned downtime) × parallel machines, and never below zero.
Effective cycle time
Measured cycle time ÷ parts per cycle.
Demonstrated capacity
Net available time × 60 ÷ effective cycle time × (1 minus scrap rate).
Downstream scrap
The scrap rates of every later operation, added together.
Requirement here
Required parts per day ÷ (1 minus downstream scrap), shown rounded up to a whole part. When downstream scrap reaches 100 percent no requirement is attainable, and the operation fails.
Part capability utilization
Requirement here ÷ demonstrated capacity.
Machine utilization
(Planned downtime of all machines + required parts per day × (1 + own scrap + downstream scrap) × effective cycle time ÷ 60) ÷ scheduled minutes of all machines. The scrap terms are an overproduction allowance added to the required rate.
Governing utilization
The higher of the two, named, because the remedies differ: more output for one, less downtime or less overproduction for the other.
Risk band
Low risk below 85 percent, medium from 85, high from 90, fail at 100 or more. An operation whose downtime consumes its whole schedule fails with no time available.
Constraint
The operation with the highest governing utilization. It sets the capacity of the line.

Two inputs are carried at a fixed resolution before any arithmetic: required parts per day to a thousandth of a part, and each scrap rate to a thousandth of a percent, both rounded up so a study never rests on less demand or less scrap than was entered. After that, rounding applies only to the figures shown. Requirements are shown rounded up, capacities rounded down, and utilization truncated to one decimal, so a figure on the page never crosses a band the line has not reached.

The template, filled in

A bracket line runs molding on two presses with four cavity tools, then an ultrasonic weld cell, then final inspection. The customer requires 2,400 parts per day.

Bracket line, 2,400 parts per day MoldingUltrasonic weld Final inspection
Entered
Shifts per day2 22
Hours per shift8 88
Parallel machines2 11
Parts per cycle4 11
Breaks and lunch, minutes60 6060
Changeover, minutes 45 every 2 days 00
Planned maintenance, minutes30 200
Other planned downtime, minutes30 00
Unplanned allowance, minutes30 2020
Measured cycle time, seconds38 2019
Scrap rate, percent1.5 10.5
Calculated
Planned downtime per machine, minutes172.5 10080
Net available time, minutes1,575 860880
Effective cycle time, seconds9.5 2019
Demonstrated capacity, parts per day9,798 2,5542,765
Downstream scrap1.5% 0.5%0%
Requirement here, parts per day2,437 2,4132,400
Part capability utilization24.8% 94.4%86.7%
Machine utilization38.3% 94.9%87.8%
Governing utilization 38.3%machine 94.9%machine 87.8%machine
Risk band LOW RISK HIGH RISK MEDIUM RISK
ConstraintNo YesNo

Read the molding column first. Its part capability utilization is only 24.8 percent, yet its machine utilization is 38.3 percent, because 345 of the presses' 1,920 scheduled minutes go to planned downtime before a part is made. Still low risk, but the gap is why a template needs both measures: on a tighter line, time binds long before output does.

The weld cell is the constraint at 94.9 percent. The line passes, at high risk: one bad shift at the weld and the day's requirement is missed, so a study that ends here should carry an action for the weld cell.

To check the example yourself, enter it in the capacity calculator. The calculator takes downtime as one total, so put 172.5 minutes in the molding downtime field.

Why a spreadsheet template drifts

Most capacity templates start as a good spreadsheet. The trouble starts around the tenth copy.

How the app replaces the spreadsheet

RateProof Capacity Study runs the formulas on this page, fixed and tested, so a study cannot drift away from its own arithmetic.

Studies stay on your iPhone or iPad, and a report leaves the device only when you share it.